A buyer wrote to me because she could not change a supplier. She needed a new purchasing organization on a partner we already had. She found the partner and chose Change, but MDG would not start a change request, so there was nothing for her to submit.
Nothing was down. The partner was already in another change request, and that request was still open. Unless a change-request type is set up for parallel processing, MDG will not let the same business partner into a second request while the first one still holds it. The record was locked by an open request, not by a broken system.
A request that is submitted and then sits with no processor is a different fault, and I wrote that case up earlier. This new request never got as far as a number.
What the screen was already showing
The search result for that business partner showed an open change request against it. I opened that request before I went anywhere near a workflow table.
The type was SUPPL2P1, Process Supplier, on data model BP. Its main entity type is BP_HEADER, and the workflow template SAP delivers with it is WS54300007. SUPPL2P1 is a single-object type with no parallel processing, so one open request holds the whole partner. The buyer only wanted to add a purchasing organization, but that did not matter. Her change was blocked even though it had nothing to do with the old one.
The status of the old request was Changes to Be Executed, which is 02 in field USMD_CREQ_STATUS of table USMD120C. It was not 05, Final Check Approved, and it was not 06, Final Check Rejected. In the standard process those are the two final statuses, and only a final status releases the partner. I always read the status text as well as the number, because some projects add statuses of their own.
The request had been raised earlier in the month for a street change. Purchasing had since dropped that change, but nobody had closed the request. And the user who created it was not the user the workflow was waiting on.
USMD1213 holds the objects in each change request, with the entity type and key. I read it for BP_HEADER with that request number and confirmed it was the request holding this partner. Finished requests can still appear in that table until they are archived, so a row there proves nothing on its own. The status in USMD120C is what tells you whether the request still blocks.
Who still had the work item
The workflow log on the change request showed the current step as an approval, sitting with a named user. The work item was still in his Business Workplace inbox in SBWP. He had neither approved nor rejected it. He was on leave, and the item had stayed where it landed.
If your landscape uses Fiori My Inbox, it is the same work item. The log is what tells me whose inbox to open.
I also checked the workflows for that request under object type BUS2250, the business object MDG uses for change requests. The same work item was there, ready, for the same user, so the log and the inbox agreed.
SM12 showed no lock entry on USMD120C for this request. That kind of lock, message USMD1A016 ("Change request locked by user"), is a different problem: someone is actively processing the request itself. Here nobody was touching it. The partner was simply sitting in a request that had never ended.
Finish the old request, or reject it
The street change was no longer wanted, and the approver was on leave with no substitute set on his inbox. In SWIA I forwarded the ready work item to the colleague covering those approvals. She opened it in SBWP, rejected it, and entered a rejection reason saying the address change had been dropped.
On the delivered SUPPL2P1 workflow, a rejection at the approval step does not end the request. It sends it back to the requester for revision. The requester withdrew it, and only then did the status move to Final Check Rejected and the workflow end. The row in USMD120C stayed, as it always does, but BP_HEADER was no longer held by an open request.
If the old change had still been right, the approver's cover would have approved it instead. Activation runs, the status moves to Final Check Approved, and only then is a new request allowed. The rule is the same on both paths: the open request has to end before the next one can start.
The buyer then created a new SUPPL2P1 request for the same partner, with the purchasing organization she needed. It got a number, and the workflow log showed the first approval step with an agent. That was the test. Had she tried again while the old request was still at status 02, it would have failed in the same place.
We left SUPPL2P1 as delivered, as a single-object type without parallel processing. Parallel change requests are switched on per change-request type, with a scope you define by entity type, and they do not apply to creating a partner. Where you use them, two requests can run side by side on the same partner as long as their scopes do not overlap. That is a design change you configure in customizing and test with real changes. It is not the fix for a forgotten inbox. A forgotten inbox is fixed by finishing the open request or rejecting it.
The review that would have caught this
An open change request is a lock on that business partner, and it stays a lock until someone finishes or rejects it. The person who can do that is whoever holds the work item. By the time the buyer wrote to me, that was no longer the person who had created the request.
On this project we now review the requests still sitting in Changes to Be Executed. For anything left over from an earlier week, I open the workflow log and name the owner. If that person is out, we forward the work item. Then we finish the request or reject it, before the next buyer discovers the lock by being unable to change a supplier.